The Reserva Zapotlán hub, Hidalgo: the developer is in, the grid is not
The Reserva Zapotlán hub covers 910.82 ha in the AIFA corridor and, since 19 August 2026, has a developer: DEWA Capital, with more than 10,100 million pesos over five phases. SENER estimates 20 MW at maturity, with the high-voltage connection about 24 km away.

Bajío Ventures · October 2026 · The welfare hubs, one by one
Reserva Zapotlán is the second-largest of Mexico’s welfare development hubs (Polos de Desarrollo Económico para el Bienestar, PODECOBI) and one of the few with a developer. It covers 910.82 ha in Zapotlán de Juárez, Hidalgo, 29 km from AIFA airport and next to the Arco Norte highway. On 19 August 2026 the Ministry of Economy (SE) presented DEWA Capital as developer, with more than 10,100 million pesos over five phases. Phase 1 works were due to start in the second half of September 2026. As of this writing we have not confirmed the start. Proyectos México lists the hub as in execution.
The fact sheet
| Field | Data |
|---|---|
| Official name | Polo de Desarrollo Económico para el Bienestar Reserva Zapotlán |
| State and municipality | Hidalgo / Zapotlán de Juárez |
| Area | 910.82 ha (corrected by clarification notice) |
| Declaration (DOF) | 30 June 2025; clarification notice 29 July 2025 |
| SE–state agreement | 15 October 2025 |
| Target sectors | Logistics, manufacturing, pharma and medical devices, automotive, aerospace |
| Developer | DEWA Capital (Frontier industrial platform), announced 19 August 2026 |
| Announced investment | More than 10,100 million pesos over 5 phases (Proyectos México: 10,106 million pesos, USD 523.6 million) |
| Status | Execution; construction planned for H2 2026 (Proyectos México, revised 18 August 2026) |
The original declaration gave 922 ha. The clarification notice corrected the area to 910.82 ha and the municipality to “Zapotlán de Juárez”. Some secondary sources still use 922 ha.
Connectivity
- Federal highway 85D and the Arco Norte (M40D).
- AIFA: 29 km. Pachuca airport: 12 km.
- Pemex pipelines: 4 km (the original text said 150 m).
- Next to the PLATAH industrial park, inside the AIFA corridor (Pachuca, Tizayuca, Zumpango, Tecámac).
- Proyectos México cites the “Aduana 50 NLU” customs facility with 470,000 t capacity, and an intermodal terminal in planning.
Energy and water
SENER, in the opinion cited by the declaration, estimates 20 MW of demand at maturity, with 8 to 12 MW over 2028–2030. Supply would be at distribution voltage while it suffices, and from the national grid above that. The nearest distribution substation is 20 km away. The high-voltage connection would be at the Tizayuca substation, about 24 km away. SENER also mentions capacity via the Parque Industrial (Pachuca), Tizayuca (Tula) and Irolo (Tulancingo) substations. The CENAGAS Cempoala–Santa Ana gas pipeline is 4 km away, with about 6.4 million cubic feet per day estimated.
Proyectos México adds fibre optic, wells, an existing wastewater plant and a larger one in planning.
The contrast is plain: 910.82 ha and 20 MW. An API pharmaceutical plant or a mid-size auto-parts plant typically needs several megawatts each. Two or three industrial tenants could use up the estimated capacity. The 24 km connection to Tizayuca has no published date. Power, not land, is this hub’s bottleneck.
What to watch
- Start of works. DEWA announced phase 1 with 1,277 million pesos for urbanization and trunk works, more than 2,000 million pesos for the first two buildings, about 5,100 direct and indirect jobs and at least 35% local hiring. Works were scheduled to start in September 2026.
- Two investment layers that the press mixes up. In December 2025 the government announced a USD 2,000 million pharmaceutical plant, with no company named. In August 2026 it announced the developer’s 10,100 million pesos. The federal figure of “more than 16,600 million pesos” appears to add a 6,500 million peso Cruz Azul cement investment in Tula, outside the hub.
- Grid capacity. 20 MW for 910.82 ha. No public source dates the grid reinforcement.
- Water. Proyectos México mentions wells, with no volume.
Our view
Zapotlán is the most substantial hub in this batch: state land, a named developer, phased amounts and a solid location in the AIFA corridor. Hidalgo is also spending 313 million pesos on infrastructure in Tolcayuca, Villa de Tezontepec and Zapotlán to prepare the hub. The state offers payroll-tax discounts of 100/75/50% over three years, and municipalities cuts of up to 50% until 2030. The federal incentive is the same in all 15 hubs: 100% immediate deduction of new fixed assets plus an extra 25% on the increase in training or innovation spending (details in the pillar piece). There is no income-tax exemption.
For an energy developer, this is the hub where talks with the developer make sense now. The gap between 20 MW and the size of the site opens room for on-site gas generation with a pipeline 4 km away, rooftop solar self-supply on the buildings, and storage to manage demand until the high-voltage connection arrives. Self-supply installations under 0.7 MW need no generation permit, which allows a building-by-building start.
Series: The 15 welfare hubs as of October 2026 · The Michoacán hub and Guanajuato: one corridor
Sources: DOF, Reserva Zapotlán hub declaration, Jun-2025 · DOF, Reserva Zapotlán clarification notice, Jul-2025 · DOF, PODECOBI tax-incentive decree, May-2025 · Proyectos México, PODECOBI Reserva Zapotlán, Aug-2026 · SE, coordination agreement with Hidalgo, Oct-2025 · Cluster Industrial, DEWA to invest over 10,000 mdp, Aug-2026 · Crónica, Reserva Zapotlán over 16,000 mdp, Aug-2026